RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Sports & Entertainment · ModernizationCompleted 2025

Professional Stadium Modernization

Three off-seasons, one modernized stadium, and every home game played where it was scheduled.

LocationSoutheast US
ClientConfidential
LocationSoutheast US
SectorSports & Entertainment
Value$480M
Size70,000 seats
DeliveryCM at Risk
Duration30 months
StatusCompleted 2025
Why it mattered

Sports and entertainment run on dates printed on tickets. Opening night is not a target; it is fixed, and the schedule has to be built backward from it.

The challenge

A professional franchise modernized its stadium over three off-seasons, adding video boards, premium seating, concourses and new building systems.

Each off-season was a hard window. Anything unfinished had to be made safe and usable for the opener, so every sprint needed a defined fallback as well as a plan.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartJan 2023
Duration30 months
HandoverJul 2025
Progress—
Work the windowsPlan the fallbackAlign every ownerRevenue spaces first
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Work the windows

Off-seasons and dark periods planned as projects of their own, with every day accounted for.

PHASE 02Plan the fallback

Any unfinished work planned in advance to be safe and usable for the next event.

PHASE 03Align every owner

Teams, operators and tenants working from one schedule toward one night.

PHASE 04Revenue spaces first

Premium seating and other revenue-critical spaces prioritized in the sequence.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01No game moved

No home game was relocated or affected by construction.

Result 02Off-seasons run as projects

Each off-season had its own baseline, resource plan and fallback scope.

Result 03Premium seats ready to sell

New premium seating was complete in time for season-ticket sales.