Hyperscale Data Center Campus
Four contractor schedules reported on track. The campus was not, and nobody could see why.
LocationDallas-Fort Worth, TXIn data centers, time is capacity and capacity is revenue. Ready-for-service dates are contractual, and a single unlinked dependency can hide months of risk behind a green report.
A hyperscale operator was building a multi-building campus where each data hall carried a contracted ready-for-service date with tenants.
Every contractor reported green. But utility energization, switchgear deliveries and integrated systems testing had never been linked in one model, and our assessment found the true critical path running through work no single contractor owned.
The whole program, on one line.
Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.
Our approach, phase by phase.
The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

The difference we made
Measured the only way that matters: whether the date and the budget held.
An integrated master schedule exposed the real path through energization and IST, and the gap sitting behind it.
Each data hall met its tenant ready-for-service date.
A weekly dashboard and recovery rhythm put choices in front of executives while those choices could still change the outcome.
What we brought to it
Integrated Master Schedules that bind design, procurement, construction and commissioning into one traceable program view, from board summary to field activity.
2.01.08Schedule Health AssessmentIndependent diagnostics against DCMA 14-Point, GAO and AACE practice that tell you, in days, how far a schedule can be relied upon and what it will take to fix it.
2.01.05Recovery SchedulingRecovery plans that restore control of late programs: diagnosed quickly, built on what is physically achievable and agreed by every party who must fund or deliver them.
2.05.01Power BI DashboardsFast, governed Power BI reporting built on sound semantic models, connected to your controls systems and designed around real decisions.
2.01.15Commissioning & Startup SchedulingSystem-based commissioning and startup schedules that carry facilities from mechanical completion to reliable operation without the familiar last-mile slip.
More Data Centers projects
Data CentersCompleted 2023Edge Data Center Program
- Value
- $260M
- Size
- 12 sites
- Client
- Confidential
Data CentersIn progress · 2026AI-Ready Liquid-Cooled Data Center
- Value
- $980M
- Size
- High-density liquid-cooled
- Client
- Confidential
HealthcareIn progress · 2027Academic Medical Center Patient Tower
- Value
- $1.15B
- Size
- 820,000 sq ft · 14 stories
- Client
- Confidential

Make your program the next one we land.
Tell us what you are building and the date your board expects. In one senior-led review you will know what it will take to hold it.