RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Data Centers · New ConstructionCompleted 2025

Hyperscale Data Center Campus

Four contractor schedules reported on track. The campus was not, and nobody could see why.

LocationDallas-Fort Worth, TX
ClientConfidential
LocationDallas-Fort Worth, TX
SectorData Centers
Value$1.4B
Size3 data halls · campus
DeliveryCM at Risk
Duration34 months
StatusCompleted 2025
Why it mattered

In data centers, time is capacity and capacity is revenue. Ready-for-service dates are contractual, and a single unlinked dependency can hide months of risk behind a green report.

The challenge

A hyperscale operator was building a multi-building campus where each data hall carried a contracted ready-for-service date with tenants.

Every contractor reported green. But utility energization, switchgear deliveries and integrated systems testing had never been linked in one model, and our assessment found the true critical path running through work no single contractor owned.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartSep 2022
Duration34 months
HandoverJul 2025
Progress—
One critical pathTest the floatFollow the long leadsCommission to contract
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01One critical path

Every contractor schedule integrated into one master, from utility energization to integrated systems testing.

PHASE 02Test the float

Independent schedule health assessments that expose float which does not really exist.

PHASE 03Follow the long leads

Switchgear, generators and cooling equipment tracked from factory slot to installation.

PHASE 04Commission to contract

Level 1 to 5 commissioning planned to meet every tenant ready-for-service date.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01One candid critical path

An integrated master schedule exposed the real path through energization and IST, and the gap sitting behind it.

Result 02Halls delivered to contract

Each data hall met its tenant ready-for-service date.

Result 03Weekly decisions

A weekly dashboard and recovery rhythm put choices in front of executives while those choices could still change the outcome.