RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Data Centers · New ConstructionIn progress · 2026

AI-Ready Liquid-Cooled Data Center

A tenant is waiting on capacity, and few comparable builds exist to schedule against.

LocationSan Antonio, TX
ClientConfidential
LocationSan Antonio, TX
SectorData Centers
Value$980M
SizeHigh-density liquid-cooled
DeliveryDesign-Build
Duration26 months
StatusTarget 2026
Why it mattered

In data centers, time is capacity and capacity is revenue. Ready-for-service dates are contractual, and a single unlinked dependency can hide months of risk behind a green report.

The challenge

A developer is delivering a high-density, liquid-cooled facility for AI computing, with a tenant already committed to the capacity.

Liquid cooling, extreme power density and immature equipment supply chains leave little historical data to plan from. Durations that look reasonable on paper have rarely been tested on a job like this one.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartMay 2024
Duration26 months
Target finishJul 2026
Progress—
One critical pathTest the floatFollow the long leadsCommission to contract
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01One critical path

Every contractor schedule integrated into one master, from utility energization to integrated systems testing.

PHASE 02Test the float

Independent schedule health assessments that expose float which does not really exist.

PHASE 03Follow the long leads

Switchgear, generators and cooling equipment tracked from factory slot to installation.

PHASE 04Commission to contract

Level 1 to 5 commissioning planned to meet every tenant ready-for-service date.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Compressed delivery under control

Design-build overlap is managed through a rolling-wave master schedule that adds detail as each package releases.

Result 02Equipment tracked from factory slot

Critical cooling and electrical equipment is followed from manufacturing slot to installation.

Result 03IST set at baseline

Integrated systems testing logic was defined in the first baseline rather than left to the final months.