Operating Room Chilled Water Plant Replacement
The plant that keeps every operating room cool was failing. It was replaced without the rooms ever noticing.
LocationAugusta, GABuilding inside a working hospital means every hour of construction is taken from patient care. The discipline is to take as little as possible, give it back on the hour agreed, and treat infection control as logic, not paperwork.
A regional hospital's chilled water plant was at the end of its life, and it served every operating room in the building. Even a brief loss of cooling would have stopped surgery.
Swapping chillers, towers and pumps meant stepping through a series of temporary cooling configurations. Each one narrowed the margin on temperature and humidity in the ORs, so each was planned with the same care as the permanent work.
The whole program, on one line.
Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.
Our approach, phase by phase.
The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

The difference we made
Measured the only way that matters: whether the date and the budget held.
OR temperature and humidity stayed inside tolerance through every cutover.
Each switchover ran from a minute-level script, walked through with facilities and clinical leads before the night it happened.
The hospital came out with N+1 redundancy on a system that had been running without a spare.
What we brought to it
Hour-by-hour shutdown and turnaround schedules that compress outage windows and return critical assets to service safely, on the date operations committed to.
2.01.07Critical Path AnalysisRigorous analysis of critical and near-critical paths that shows leadership exactly where attention and money will move the date, and where they will not.
2.01.15Commissioning & Startup SchedulingSystem-based commissioning and startup schedules that carry facilities from mechanical completion to reliable operation without the familiar last-mile slip.
More Healthcare projects
HealthcareCompleted 2024Ambulatory HealthPlace Campus
- Value
- $185M
- Size
- 160,000 sq ft
- Client
- Confidential
HealthcareCompleted 2023Cardiothoracic Robotic Operating Suites
- Value
- $64M
- Size
- 38,000 sq ft
- Client
- Confidential
HealthcareCompleted 2023Multi-Site Specialty Pharmacy Program
- Value
- $48M
- Size
- 14 sites
- Client
- Confidential

Make your program the next one we land.
Tell us what you are building and the date your board expects. In one senior-led review you will know what it will take to hold it.