RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Healthcare · RenovationCompleted 2023

Cardiothoracic Robotic Operating Suites

Open-heart surgery runs here every weekday. The rebuild had to fit around it, hour by hour.

LocationAtlanta, GA
ClientConfidential
LocationAtlanta, GA
SectorHealthcare
Value$64M
Size38,000 sq ft
DeliveryCM at Risk
Duration18 months
StatusCompleted 2023
Why it mattered

Building inside a working hospital means every hour of construction is taken from patient care. The discipline is to take as little as possible, give it back on the hour agreed, and treat infection control as logic, not paperwork.

The challenge

An academic hospital set out to rebuild its cardiothoracic operating suites for a new generation of surgical robotics, inside the same building where its surgeons operate on hearts every day.

Each room could leave service only in windows negotiated with surgery, anesthesia and infection prevention. A missed window meant cancelled cases and patients rebooked weeks out, so every slip carried a clinical cost before it carried a financial one.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartJan 2022
Duration18 months
HandoverJul 2023
Progress—
Capture the constraintsScript every outagePublish the look-aheadReturn rooms on time
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Capture the constraints

Surgical calendars, ICRA classes, utility dependencies and clinical sign-offs written into the schedule as hard logic.

PHASE 02Script every outage

Each shutdown and room turnover planned hour by hour and walked through with facilities and clinical leadership beforehand.

PHASE 03Publish the look-ahead

A rolling two-week view issued to clinicians in plain language, so no department was ever caught unaware.

PHASE 04Return rooms on time

Commissioning, air balancing, testing and terminal cleaning sequenced so each space went back to care on its scheduled hour.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01No unplanned room closures

Every suite left and returned to service on the dates agreed with clinical leadership, across eighteen months of work.

Result 02Infection control in the logic

Barriers, negative pressure and inspections were hard predecessors, so no one could skip them to buy back time.

Result 03First robotic case on plan

Installation, calibration and team training ran as one critical chain to the first scheduled case.