RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Healthcare · ExpansionCompleted 2022

Hospital Central Laundry Expansion

Every clean sheet on a major medical campus passes through this plant. It nearly doubled in capacity without a lost shift.

LocationJacksonville, FL
ClientConfidential
LocationJacksonville, FL
SectorHealthcare
Value$38M
Size72,000 sq ft
DeliveryDesign-Build
Duration16 months
StatusCompleted 2022
Why it mattered

In a working plant, the most expensive thing on site is downtime. The schedule's job is to let construction happen without production ever feeling it.

The challenge

A large medical campus needed to nearly double its central laundry capacity to keep pace with new beds and operating rooms. The plant ran around the clock, every day of the year.

Tunnel washers, dryers and conveyors had to be installed and commissioned beside live production. Every hour of downtime was bought back through third-party processing, at a premium the owner could read on each invoice.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartMar 2021
Duration16 months
HandoverJul 2022
Progress—
Learn the plantScript the tie-insBring vendors insideRamp to throughput
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Learn the plant

Production calendars, critical utilities and acceptable outage windows mapped with operations before logic is drawn.

PHASE 02Script the tie-ins

Every connection to the live process planned to the hour, each with a tested fallback.

PHASE 03Bring vendors inside

Equipment fabrication and delivery held as schedule activities, not in separate spreadsheets.

PHASE 04Ramp to throughput

Startup, trials and handover sequenced to reach full output on the target date.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Downtime confined to plan

Tie-ins landed in scripted weekend windows, each with a tested fallback if a cutover ran long.

Result 02Vendors inside the schedule

Fabrication and delivery were tracked as schedule activities, so a late shipment registered as float consumed rather than as a surprise on site.

Result 03Capacity ahead of demand

The new line reached full throughput before the next patient tower opened its doors.