RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Cultural & Civic · New ConstructionCompleted 2022

Large Mammal Habitat

Animal transfer dates do not move. The habitat was built around them.

LocationYulee, FL
ClientConfidential
LocationYulee, FL
SectorCultural & Civic
Value$18M
Size8-acre habitat
DeliveryDesign-Build
Duration12 months
StatusCompleted 2022
Why it mattered

Civic projects belong to the public, and the public notices when a date slips. Elected officials, donors and residents deserve a schedule that tells them the truth early.

The challenge

A conservation center built a new habitat for large mammals, with barns, water features and visitor viewing areas.

Animal transfers and quarantine periods were arranged with other institutions and set dates construction could not shift. Noise and activity near the animals had to be managed throughout.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartJul 2021
Duration12 months
HandoverJul 2022
Progress—
Respect the windowsMake permits milestonesReport for the publicWork to opening day
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Respect the windows

Environmental, seasonal and event windows built in as hard constraints from the first baseline.

PHASE 02Make permits milestones

Every agency approval tracked as a dated milestone with a named owner.

PHASE 03Report for the public

Progress reporting clear enough to share with residents, donors and elected officials without translation.

PHASE 04Work to opening day

The celebration date held as the critical finish, with every activity driving toward it.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Quiet where it counted

Piling, demolition and other loud work were scheduled away from occupied enclosures and keeper-defined sensitive periods.

Result 02Ready before the trailers arrived

Barns, water features and fencing were signed off ahead of every planned transfer.

Result 03Open for the visitor season

Public viewing areas welcomed guests at the start of the season, as the center had planned.

Your program, under command

Make your program the next one we land.

Tell us what you are building and the date your board expects. In one senior-led review you will know what it will take to hold it.