RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Cultural & Civic · New ConstructionCompleted 2021

Community Family Wellness Center

A community-funded wellness center, with summer programs full before the doors existed.

LocationJacksonville, FL
ClientConfidential
LocationJacksonville, FL
SectorCultural & Civic
Value$24M
Size50,000 sq ft
DeliveryDesign-Build
Duration14 months
StatusCompleted 2021
Why it mattered

Civic projects belong to the public, and the public notices when a date slips. Elected officials, donors and residents deserve a schedule that tells them the truth early.

The challenge

A nonprofit built a family wellness center with pools, gyms and childcare, funded largely by community donations.

Every dollar was visible to donors, and opening was tied to summer programs families had already signed up for. The board needed both the date and the budget to hold.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartMay 2020
Duration14 months
HandoverJul 2021
Progress—
Respect the windowsMake permits milestonesReport for the publicWork to opening day
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Respect the windows

Environmental, seasonal and event windows built in as hard constraints from the first baseline.

PHASE 02Make permits milestones

Every agency approval tracked as a dated milestone with a named owner.

PHASE 03Report for the public

Progress reporting clear enough to share with residents, donors and elected officials without translation.

PHASE 04Work to opening day

The celebration date held as the critical finish, with every activity driving toward it.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Camp opened on day one

Swim lessons and childcare began on the date families had registered for.

Result 02Reports donors could follow

Monthly progress notes, written in plain language, gave the capital campaign something concrete to show.

Result 03Within the raised budget

Schedule-linked cost-to-complete forecasts surfaced pressure early enough to value-engineer rather than overrun.