RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Healthcare · New ConstructionCompleted 2024

Comprehensive Cancer Center & Proton Therapy

The cyclotron's delivery slot was fixed a year out by its manufacturer. Everything else had to bend to that day.

LocationPhoenix, AZ
ClientConfidential
LocationPhoenix, AZ
SectorHealthcare
Value$410M
Size260,000 sq ft
DeliveryCM at Risk
Duration38 months
StatusCompleted 2024
Why it mattered

A late hospital opening is measured in patients, not penalties: a family driving further for care, a surgeon without a room, a community told to wait. Boards need a date they can announce and defend, and we build the schedule that earns it.

The challenge

A health system was bringing proton therapy to its region for the first time. The treatment vault walls are meters thick, and the manufacturer set the cyclotron's delivery slot more than twelve months in advance.

Mass concrete pours, shielding inspections, rigging routes and crane access all had to converge on a single day. Missing it meant rejoining the manufacturer's queue, a delay measured in months and a cost no contingency had been sized for.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartMay 2021
Duration38 months
HandoverJul 2024
Progress—
Assess every scheduleArchitect by roomCommand each periodClose into activation
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Assess every schedule

An independent health check of each schedule in play, then a single integrated critical path linking design, procurement, construction and medical equipment.

PHASE 02Architect by room

Equipment, IT and life-safety systems tied to the readiness of individual rooms and departments, not whole floors.

PHASE 03Command each period

Two-week data dates, earned value and quantified P50/P80 risk, so leadership could act months ahead rather than weeks.

PHASE 04Close into activation

Commissioning, inspections, clinical training and move-in sequenced as one critical chain to the first patient.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Ready on delivery day

The vault was poured, inspected and clear for rigging on the morning the cyclotron arrived.

Result 02Vendor plan inside the master

The equipment vendor's installation sequence was built into the master schedule activity by activity, with float to the delivery date reported every week.

Result 03First treatment on plan

Commissioning and clinical validation finished in time for the planned first patient treatment.