RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Food & Beverage · New ConstructionIn progress · 2026

Commercial-Scale Precision Fermentation Facility

No playbook exists for this plant at commercial scale. The schedule is being written as the engineering matures.

LocationConfidential, US
ClientConfidential
LocationConfidential, US
SectorFood & Beverage
Value$340M
SizeCommercial-scale bioprocess
DeliveryProgressive Design-Build
Duration32 months
StatusTarget 2026
Why it mattered

Food and beverage plants live by market windows: peak season, retail launches, distribution contracts. A schedule that misses the window does not lose weeks; it loses the year.

The challenge

A food technology company is building one of the first commercial-scale precision fermentation plants, producing proteins without animals.

Process design is still evolving as construction starts. A conventional fixed baseline would be out of date within weeks, yet investors still need a forecast they can rely on.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartNov 2023
Duration32 months
Target finishJul 2026
Progress—
Protect productionPut equipment on the pathIntegrate the vendorsValidate and ramp
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Protect production

Shutdowns placed in low-demand periods, with every outage planned to the hour.

PHASE 02Put equipment on the path

Process equipment tracked from factory slot to setting on its foundation.

PHASE 03Integrate the vendors

Line vendors, automation and building trades working to one critical path.

PHASE 04Validate and ramp

Line trials, food-safety validation and ramp-up scheduled as real work with real durations.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Rolling-wave detail

The schedule adds detail as each design package matures, without losing sight of the critical path.

Result 02Investor-grade forecasts

Monthly forecasts with stated confidence levels give investors a defensible view of the program.

Result 03Startup in the first baseline

Commissioning and qualification logic was present from the first issue, not bolted on late.