RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Food & Beverage · ExpansionCompleted 2023

Ice Cream Plant Upgrade & Expansion

One of the brand's largest plants, rebuilt line by line without a single summer shipment missed.

LocationOntario, Canada
ClientConfidential
LocationOntario, Canada
SectorFood & Beverage
Value$210M
SizeProduction & cold storage
DeliveryEPCM
Duration30 months
StatusCompleted 2023
Why it mattered

Food and beverage plants live by market windows: peak season, retail launches, distribution contracts. A schedule that misses the window does not lose weeks; it loses the year.

The challenge

A global food brand expanded and modernized one of its largest ice cream plants, adding production lines and automated cold storage.

Every hour of shutdown in peak season meant empty freezer space at retail. Cutovers had to land in carefully chosen low-demand windows, and a window missed in spring could not be recovered until autumn.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartJan 2021
Duration30 months
HandoverJul 2023
Progress—
Protect productionPut equipment on the pathIntegrate the vendorsValidate and ramp
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Protect production

Shutdowns placed in low-demand periods, with every outage planned to the hour.

PHASE 02Put equipment on the path

Process equipment tracked from factory slot to setting on its foundation.

PHASE 03Integrate the vendors

Line vendors, automation and building trades working to one critical path.

PHASE 04Validate and ramp

Line trials, food-safety validation and ramp-up scheduled as real work with real durations.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01No summer output lost

The program cost no production during peak season in any year of the work.

Result 02Every outage inside its window

Each planned shutdown closed out within its allotted hours.

Result 03Validation treated as real work

Line trials and food-safety validation carried durations and logic in the schedule, not a closing assumption.