RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Manufacturing · ExpansionCompleted 2022

Aerospace Components Facility

The airframer set the date. Every machine foundation had to be ready before its machine.

LocationWichita, KS
ClientConfidential
LocationWichita, KS
SectorManufacturing
Value$160M
Size340,000 sq ft
DeliveryDesign-Build
Duration22 months
StatusCompleted 2022
Why it mattered

New manufacturing capacity has customers waiting on it before the slab is poured. The first production run is the date that matters, and everything else is a means to it.

The challenge

An aerospace supplier expanded a facility to produce structural components for a new aircraft program, on a timetable set by the airframer.

Heavy machine foundations, overhead cranes and quality certifications all sat on the critical path. A late foundation would hold a machine, and a late machine would hold first-article inspection.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartSep 2020
Duration22 months
HandoverJul 2022
Progress—
Overlap with controlTrack outside dependenciesMeasure, do not estimatePlan the first run
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Overlap with control

Phased building turnover planned so tool installation could start well before the building was complete.

PHASE 02Track outside dependencies

Utility service, permits and equipment deliveries held as critical external milestones.

PHASE 03Measure, do not estimate

Earned value and quantity-based progress in place of opinion-based percent complete.

PHASE 04Plan the first run

Commissioning and production ramp-up scheduled with operations from the first baseline.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01First article on the airframer's date

First-article inspection was completed on the date the aircraft program required.

Result 02Foundations first

Machine foundations were sequenced ahead of enclosure, so equipment could set on arrival.

Result 03Certification scheduled

Quality certification steps carried durations and owners inside the schedule.