
Refinery Turnaround Program
Every day offline costs a refinery dearly. This unit came back two days ahead of plan.
LocationGulf CoastIn energy, the schedule is a financial instrument. Interconnection dates, outage windows and tax-credit deadlines turn days into millions, and every hour offline has a price.
A refinery planned a major turnaround with thousands of maintenance activities inside a forty-five-day window.
Each day offline meant lost production, so precision in planning paid for itself many times over. Scope discovered once equipment was opened had to be absorbed without breaking the window.
The whole program, on one line.
Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.
Our approach, phase by phase.
The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

The difference we made
Measured the only way that matters: whether the date and the budget held.
The unit returned to service forty-three days after shutdown, against a forty-five-day plan.
Hour-level schedules coordinated every craft and were statused at each shift change, so discovered scope was placed within hours.
Safety-critical activities kept their full durations; recovery came from sequence, not shortcuts.
What we brought to it
Hour-by-hour shutdown and turnaround schedules that compress outage windows and return critical assets to service safely, on the date operations committed to.
2.02.06Progress MeasurementQuantity-based, field-verified progress measurement that turns physical work into numbers owners, lenders and auditors will accept.
2.01.10Resource LoadingLabor, equipment and cost loading that turns a schedule into a feasible plan for people, plant and cash, and the foundation for earned value.
2.01.07Critical Path AnalysisRigorous analysis of critical and near-critical paths that shows leadership exactly where attention and money will move the date, and where they will not.
More Power & Energy projects
Power & EnergyCompleted 2024Solar + Storage Portfolio
- Value
- $820M
- Size
- 4 sites
- Client
- Confidential
Power & EnergyCompleted 2022Combined-Cycle Power Plant Upgrade
- Value
- $340M
- Size
- 1,100 MW plant
- Client
- Confidential
HealthcareIn progress · 2027Academic Medical Center Patient Tower
- Value
- $1.15B
- Size
- 820,000 sq ft · 14 stories
- Client
- Confidential

Make your program the next one we land.
Tell us what you are building and the date your board expects. In one senior-led review you will know what it will take to hold it.



