RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Power & Energy · TurnaroundCompleted 2023

Refinery Turnaround Program

Every day offline costs a refinery dearly. This unit came back two days ahead of plan.

LocationGulf Coast
ClientConfidential
LocationGulf Coast
SectorPower & Energy
Value$260M
Size45-day outage
DeliveryEPC
Duration14 months
StatusCompleted 2023
Why it mattered

In energy, the schedule is a financial instrument. Interconnection dates, outage windows and tax-credit deadlines turn days into millions, and every hour offline has a price.

The challenge

A refinery planned a major turnaround with thousands of maintenance activities inside a forty-five-day window.

Each day offline meant lost production, so precision in planning paid for itself many times over. Scope discovered once equipment was opened had to be absorbed without breaking the window.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartMay 2022
Duration14 months
HandoverJul 2023
Progress—
Plan to the hourProtect commercial datesMeasure progress objectivelyReturn to service
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Plan to the hour

Outages and turnarounds planned at hour level, with every craft and permit accounted for.

PHASE 02Protect commercial dates

Interconnection, tax-credit and offtake milestones held as hard dates.

PHASE 03Measure progress objectively

Quantity-based progress and earned value on every site, every period.

PHASE 04Return to service

Startup and testing sequenced to bring capacity on, or back on, by the committed date.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Back on stream two days early

The unit returned to service forty-three days after shutdown, against a forty-five-day plan.

Result 02Updated every shift

Hour-level schedules coordinated every craft and were statused at each shift change, so discovered scope was placed within hours.

Result 03Safety never traded for time

Safety-critical activities kept their full durations; recovery came from sequence, not shortcuts.