
Combined-Cycle Power Plant Upgrade
More megawatts from the same plant, back online before the summer peak.
LocationOklahomaIn energy, the schedule is a financial instrument. Interconnection dates, outage windows and tax-credit deadlines turn days into millions, and every hour offline has a price.
A utility upgraded turbines and controls at a combined-cycle plant to increase output and efficiency.
The work had to be finished before summer peak demand, when the grid needs every megawatt. The turbine manufacturer's plan and the site plan were separate documents built on different assumptions.
The whole program, on one line.
Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.
Our approach, phase by phase.
The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

The difference we made
Measured the only way that matters: whether the date and the budget held.
The plant returned to service ahead of summer peak demand.
Critical path analysis of the combined plan removed several days from the original outage duration.
The turbine manufacturer's schedule was folded into the master outage plan, with each assumption reconciled.
What we brought to it
Hour-by-hour shutdown and turnaround schedules that compress outage windows and return critical assets to service safely, on the date operations committed to.
2.01.07Critical Path AnalysisRigorous analysis of critical and near-critical paths that shows leadership exactly where attention and money will move the date, and where they will not.
2.01.15Commissioning & Startup SchedulingSystem-based commissioning and startup schedules that carry facilities from mechanical completion to reliable operation without the familiar last-mile slip.
More Power & Energy projects
Power & EnergyCompleted 2024Solar + Storage Portfolio
- Value
- $820M
- Size
- 4 sites
- Client
- Confidential
Power & EnergyCompleted 2023Refinery Turnaround Program
- Value
- $260M
- Size
- 45-day outage
- Client
- Confidential
Food & BeverageCompleted 2024Food Manufacturing ASRS Building Addition
- Value
- $96M
- Size
- 120 ft high-bay ASRS
- Client
- Confidential

Make your program the next one we land.
Tell us what you are building and the date your board expects. In one senior-led review you will know what it will take to hold it.



