RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Hospitality · New ConstructionIn progress · 2026

Downtown Hotel & Convention Tower

Conventions are booked years in advance. This hotel's opening was sold before the structure topped out.

LocationDallas, TX
ClientConfidential
LocationDallas, TX
SectorHospitality
Value$560M
Size1,000 keys
DeliveryCM at Risk
Duration38 months
StatusTarget 2026
Why it mattered

Hospitality depends on guests who should never know construction is happening, and on opening dates sold long before the building is finished.

The challenge

A developer is building a thousand-room convention hotel linked to the city's convention center.

Major conventions have already been booked around the opening date. A late opening would mean relocating events, with financial and reputational consequences for the developer and the city.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartMay 2023
Duration38 months
Target finishJul 2026
Progress—
Guests firstBookings as milestonesSequence FF&EIndependent assurance
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Guests first

Noise, access and room blocks planned around the guest day.

PHASE 02Bookings as milestones

Opening and room-return dates tied directly to reservations and events.

PHASE 03Sequence FF&E

Furniture and fit-out deliveries scheduled floor by floor against room readiness.

PHASE 04Independent assurance

Independent schedule reviews giving owners and lenders a view separate from the builder's.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Bookings set the milestones

Each confirmed convention is held as a hard milestone, with float to it reported every month.

Result 02Independent comfort for lenders

A monthly independent schedule review gives the financing parties a view separate from the builder's own.

Result 03FF&E matched to rooms

Furniture deliveries are sequenced floor by floor against room readiness, keeping the loading dock clear.