RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Water & Wastewater · ExpansionCompleted 2025

Groundwater Supply System Expansion

Forty-eight miles of pipe, new wells and a treatment plant, all converging on one in-service date.

LocationRosanky, TX
ClientConfidential
LocationRosanky, TX
SectorWater & Wastewater
Value$265M
Size48 miles of pipeline
DeliveryCM at Risk
Duration36 months
StatusCompleted 2025
Why it mattered

Water infrastructure is invisible until it fails. These programs protect public health for decades and must be built while every tap keeps running, under the scrutiny of ratepayers and funding agencies.

The challenge

A regional water authority needed to expand groundwater supply to member cities in one of the fastest-growing corridors it serves.

Right-of-way acquisition, river crossings and a new treatment facility each carried independent risk, and all three fed the same in-service date. Easements alone touched hundreds of parcels, and any one of them could stall a pipeline spread.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartJul 2022
Duration36 months
HandoverJul 2025
Progress—
Structure the programMatch cash to fundingPlan the live tie-insKeep a defensible record
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Structure the program

Projects, funding sources, permits and outage windows integrated into one master schedule.

PHASE 02Match cash to funding

Cost forecasts aligned to state and federal draws and board approval cycles, so committed money keeps working.

PHASE 03Plan the live tie-ins

Bypasses and service outages placed in low-demand seasons, each with a tested contingency.

PHASE 04Keep a defensible record

Contemporaneous schedule records maintained to withstand any audit, review or claim.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01In-service date met

Water reached member cities on the committed date.

Result 02Parcels tracked one by one

Easements were scheduled parcel by parcel and reviewed weekly, so crews never mobilized to land the authority did not yet hold.

Result 03A record built to be tested

Contemporaneous schedule records were kept to a standard that would stand up to scrutiny of any claim.