RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Semiconductor · ExpansionCompleted 2024

Advanced Packaging Cleanroom Expansion

A new cleanroom beside a live production floor, where improvisation was never an option.

LocationTaylor, TX
ClientConfidential
LocationTaylor, TX
SectorSemiconductor
Value$310M
Size120,000 sq ft cleanroom
DeliveryCM at Risk
Duration24 months
StatusCompleted 2024
Why it mattered

In advanced technology and life sciences, the building is an instrument. Utilities, cleanrooms and validation must be right the first time, because the equipment and products that follow are worth far more than the structure.

The challenge

A semiconductor company expanded its advanced packaging cleanroom alongside operating production.

Cleanliness protocols, vibration limits and live-plant tie-ins left no margin for decisions made on the fly. Every activity near production needed its sequence, duration and controls agreed in advance.

Schedule at a glance

The whole program, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's data date.

StartJul 2022
Duration24 months
HandoverJul 2024
Progress—
Utilities firstOwn the interfacesCoordinate dailyQualify and validate
How we held the date

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Utilities first

Utility systems sequenced to be commissioned before tool or process installation begins.

PHASE 02Own the interfaces

Hundreds of contractor interfaces held as dated, owned milestones in one integrated schedule.

PHASE 03Coordinate daily

Look-ahead planning that aligns thousands of daily workers in constrained spaces.

PHASE 04Qualify and validate

Commissioning, qualification and validation built into the schedule from the first baseline.

What changed

The difference we made

Measured the only way that matters: whether the date and the budget held.

Result 01Certified first time

The cleanroom met its ISO classification at first certification.

Result 02Production untouched

Construction did not interrupt live production at any point.

Result 03Tools in on the owner's date

Tool move-in began on the date the owner had planned.