RichardBarkleyProject Controls & Capital Advisory
2.0 — WHAT WE DO

6 practices.
49 services.

All practices & services →
2.03 · 7 services

Owner's Advisory & Assurance

Independent senior counsel for owners, boards and investors, from investment decision through recovery and handover.

Open
2.05 · 5 services

Controls Intelligence

Power BI, executive analytics and forecasting that give capital leaders decision-grade foresight.

Open
2.06 · 6 services

The Barkley Institute

Practitioner-taught courses and executive education in P6, scheduling, controls and delay analysis.

Open
Featured practice

Command of the critical path.

1.0 — WHO WE ARE

Independent. Senior. Decisive.

The controls partner owners call when the date cannot move.

Overview
3.0 — MARKETS

Sector fluency. One standard.

We know where each sector hides its schedule risk.

Overview
4.0 — PROJECTS

Representative work. Every client confidential.

60 featured projects across 17 sectors. Every client confidential.

Overview
7.0 — INSIGHTS

Decision-grade thinking.

Field notes, papers and briefings for the people who fund and build.

Overview
9.0 — CAREERS

Do the most consequential work of your career.

For planners, cost engineers and analysts who want their judgment to matter.

Overview
Representative engagement · Water & WastewaterREF 4.3.6

Resolving a contested delay on a treatment plant expansion

Forensic schedule analysis and claims support that moved a stalled dispute to an evidence-based settlement.

FIG. 01 — Resolving a contested delay on a treatment plant expansion
MarketWater & Wastewater
RegionUnited States
RoleForensic scheduling
EngagementClaim resolution
Ref4.3.6
StatusRepresentative
The challenge

Two parties, two narratives, one plant still to finish.

A wastewater treatment plant expansion finished well beyond its contract completion date. The contractor attributed the delay to the owner; the utility pointed to contractor performance. Each side had schedules that appeared to support its position.

With public funds at stake and the parties still working together on site, both needed an analysis they could understand and test.

Representative engagement. Client identity withheld; specifics anonymized and illustrative.

Our approach

How we turned it around

We let the contemporaneous record speak, window by window, with every step open to inspection.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Reconstruct

Schedule updates, daily reports and correspondence were assembled into a verified record, with each update's data date and logic changes documented.

PHASE 02Analyze

Windows analysis traced the critical path through each period and identified what moved it.

PHASE 03Apportion

Delay was allocated between the parties, including periods of concurrency, on stated and consistent criteria.

PHASE 04Resolve

Findings were presented in plain terms designed to support negotiation rather than prolong it.

What changed

The difference we made

The parties moved from entrenched positions to a settlement grounded in the record.

Result 01An analysis both sides could test

A transparent method with every assumption stated.

Result 02Fair apportionment

Delay allocated on evidence rather than assertion.

Result 03Relationship preserved

Settlement reached without the cost of formal proceedings.

Services engaged
The analysis was so clear that the argument simply ran out of room.
Representative client perspective